Calculate expectation damages and reliance damages numbers


Problem

Suppose a construction company is hired to create a new economics building for CSUN. Let V = $100,000; R = $5,000; P = $75,000.

1. Calculate expectation damages and reliance damages given these numbers. Suppose the builder's production costs, C, are uncertain at the time the contract is made.

2. Over what range of C is it efficient for the builder to breach?

3. Over what ranges of C will the builder actually breach under expectation damages, reliance damages, and zero damages?

4. Suppose the builder's cost of production turns out to be $125,000. Will performance occur?

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Calculate expectation damages and reliance damages numbers
Reference No:- TGS03261732

Expected delivery within 24 Hours