Calculate ES, LS, EF, LF, and slack time for the activities in Exercise .

Exercise :
Given the diagram shown in Figure EX 13.2, with duration times for activities A through L:

a. Identify the paths and path duration times.

b. Determine the critical path.

2348_Path Diagram.jpg