Calculate a fixed period system with a 90 service cycle


Calculate a fixed period system with a 90% service cycle level

Demand for widgets is 52,000 widgets/year

Ordering Cost is $60 per order. Unit Cost is $5.00

The Carrying Charge is 20%

Demand is 1000 per week

Lead Time is 2 weeks

Standard deviation of demand is 300/week

Calculate a fixed quantity system with 90% service cycle level.