By how many days should each activity be crashed to reduce


What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4? days?

Activity

Normal Time? (days)

Crash Time? (days)

Normal Cost

Total Cost with Crashing

Immediate? Predecessor(s)

A

5

4

$800

$1,100

-

B

9

7

$200

$600

-

C

6

5

$600

$650

-

D

8

5

$750

$1,500

A

E

6

4

$1,200

$1,650

C

By how many days should each activity be crashed to reduce the project completion time by 4? days? Fill in the table below.

?(Enter your responses as whole numbers.?)

Activity

Each Activity Should be Reduced BY

?(days)

A


B


C


D


E


The total cost of crashing the project by 4 days is $___. ?(Enter your response as a whole number.?)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: By how many days should each activity be crashed to reduce
Reference No:- TGS02661998

Expected delivery within 24 Hours