Burrito king a new fast-food franchise opening up


Question: Burrito King (a new fast-food franchise opening up nationwide) has successfully automated burrito production for its drive-up fast-food establishments. The Burro-Master 9000 requires a constant 50 seconds to produce a batch of burritos. It has been estimated that customers will arrive at the drive-up window according to a Poisson distribution at an average of one every 55 seconds. To help determine the amount of space needed for the line at the drive-up window. What is the average waiting line length (in cars)? What is the average number of cars in the system (both in line and at the window)? What is the expected average time in the system, in minutes?