Burns boats wants to assemble 50 boats per eight-hour day


Burns Boats wants to assemble 50 boats per eight-hour day using a production line. Total task time for each boat is 45 minutes.

a. What is the takt time? What is the theoretical minimum number of workstations needed?

 

b. Suppose the longest individual task takes four minutes. Will Burns be able to accomplish its goal? Justify your answer.