Budget analyst


You've a project budget of $500,000. The project is a 10 month project and the budget analyst planned to spend $50,000 per month on the project. At month 6, you review the project status and you realize the project is 40% complete. Assume you are at the end of month 6 and will include month 6's work into your EV calculation. The project has spent $425,000 to date. Using the formulas from your book, answer the following questions:

Calculate the following values:

• PV

• EV

• AC

• SV

• CV

• BAC

• EAC

• CPI

• SPI