Both no and nc connections are available for the level


Prepare a PLC ladder program for the system of given Problem and given Figure with the following added requirements:

(1) The system should cycle 100 times and then quit, and

(2) during each cycle, there should be a 1.5-minute delay after filling before the empty phase starts. The PLC tick time is 10 ms.

Problem
When turned ON, the tank system of Figure 44 alternately fills to level L and then empties to level E. The level switches are activated on a rising level. Both NO and NC connections are available for the level switches and the ON/OFF push buttons. Prepare a physical ladder diagram for this system.

2072_Figure 08.jpg

Request for Solution File

Ask an Expert for Answer!!
Electrical Engineering: Both no and nc connections are available for the level
Reference No:- TGS02189349

Expected delivery within 24 Hours