Boeing commercial airplane company is looking to


Boeing Commercial Airplane Company is looking to manufacture 10 new aircrafts. They have decided to manufacture Boeing 737 and Boeing 777 aircrafts. However they have only $120,000,000 to spend. While each Boeing 777 costs $20,000,000, each Boeing 737 costs $10,000,000. Also Boeing has to complete the manufacturing process within 6 months. It takes 12 days to manufacture a Boeing 737 while 2 months to manufacture a Boeing 777. If the profit is $5000000 for each Boeing 777 and $3000000 for each Boeing 737, calculate the optimal mix.