Bcom 220 project planning control capstone assignment a


PROJECT PLANNING & CONTROL (CAPSTONE) ASSIGNMENT -

Please print PDFs of the following reports:

Print the following Daily Bar Charts, list the activities in ES/EF sequence, show each activity happening as soon as possible, and include the float bar. Remember to make the reports look professional; organized, labeled etc. Take the time to read each report carefully and make sure the schedule looks like it should. You should be able to correct any mistakes by a careful examination of each schedule and thereby earn a high grade on this assignment.

1. A separate bar chart for each of the following:

A. Crane

B. Backhoe

C. Piledriver

D. Concrete Pump

E. Girder Supplier

F. All concrete pours

2. Overall bar chart schedule showing all activities.

3. A bar chart showing that one road will always be open, or that only one will be closed, at a time.

Note: After creating PDFs of the reports check to see if they make sense to you, Look for overlaps on equipment; if there is sufficient float so that the available equipment can be worked within the float that is ok. You can do this project under about 90 days. To ensure a high grade, make certain you carefully read the reports.

Attachment:- Assignment Files.rar

Request for Solution File

Ask an Expert for Answer!!
Dissertation: Bcom 220 project planning control capstone assignment a
Reference No:- TGS02770453

Expected delivery within 24 Hours