Based on the table below perform resource leveling what is


Based on the table below, perform resource leveling. Assume that each task can be performed independently of the other tasks. What is the completion date for the project after resource leveling? Please present your answer using the table format used in the text, showing before and after.

Task                    Workers Needed                        Scheduled Day(s)             

1                                         3                                         1, 2, 3

2                                         2                                         2,3,4,5

3                                         2                                         2, 3, 4

4                                         1                                         5, 6, 7

5                                         3                                         7, 8, 9

6                                         2                                         10