Matador Crank Company uses a machine that can produce 100 cranks per hour. The firm operates 12 hours per day, five days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 95% of the available time. Based on experience with other products, the firm expect to achieve an efficiency level of 85% for the cranks. What is the expect weekly output of cranks?