Average setup time on a certain production machine is 60 hr


Average setup time on a certain production machine is 6.0 hr. Average batch size is 40 parts, and average operation cycle time is 2.5 min. The reliability of this machine is characterized by mean time between failures of 40 hr and a mean time to repair of 35 min. If availability is ignored, what is the average hourly production rate of the machine? Taking into account the availability of the machine, determine its average hourly production rate, Suppose that availability only applied during the actual run time of the machine and not the setup time. Determine the average hourly production rate of the machine under this scenario.