Average duration and variance of each activity the


Project Evaluation and Review Technique

Index

[asks

Best
Duration

%lost Likely
Duration

NVorst
Duration

A

Market Research

4

8

10

B

Cost Analysis

2

4

5

C

Product Design

8

12

14

D

Development Analysis

7

10

13

E

Developing Product Model

6

8

16

F

Filing Contracts

6

12

18

G

Product Testing

7

10

15

H

Pricing

6

8

10

I

Sales/Marketing Planning

4

6

12

J

Sales Force Training

2

4

6

a. Average duration and variance of each activity?

b. The critical path on average is?

c. The average duration of the critical path found in (b)?

d. Variance of the duration of the critical path found in (b)?

e. The probability of the project is being completed within 58 weeks is??