Automated plant was finished and ready


January 2, 2010, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2011. Expenditures for the construction were as follows:

  • January 2, 2010 $200,000
  • September 1, 2010 600,000
  • December 31, 2010 600,000
  • March 31, 2011 600,000
  • September 30, 2011 400,000

Indian River Groves borrowed $1,100,000 on a construction loan at 12% interest on January 2, 2010. This loan was outstanding during the construction period. The company also had $4,000,000 in 9% bonds outstanding in 2010 and 2011.
The interest capitalized for 2010.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Automated plant was finished and ready
Reference No:- TGS0708733

Expected delivery within 24 Hours