Auto data produces custom engineering testing equipment


Auto Data produces custom engineering testing equipment. The following six orders are currently in the design department: Job Time Since Arrival (weeks ago) Process Time (weeks) Due Date (weeks from now) A 5 3 7 B 6 8 14 C 2 4 6 D 4 10 15 E 3 5 12 F 7 10 18 a) Create a schedule using the first-come first-serve (FCFS) rule, calculating the average flow time and average weeks past due. b) Create a schedule using the earliest due date (EDD) rule, calculating the average flow time and average weeks past due. c) Which rule gives the best schedule based on average flow time and average weeks past due?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Auto data produces custom engineering testing equipment
Reference No:- TGS02923469

Expected delivery within 24 Hours