Athletics inc completed job no c04 during 2015 the job cost


Question: Athletics, Inc. completed Job No. C04 during 2015. The job cost sheet listed the following: Direct materials $110,000 Direct labor $60,000 Manufacturing overhead applied $40,000 Units produced 3,000 units Re-cap: Units sold 1,800 units Finished goods on hand 1,200 units Units produced 3,000 units

a) What is the per-unit cost to manufacture one unit?

b) How much is the cost of the 1,200 units of finished goods on hand from this job?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Athletics inc completed job no c04 during 2015 the job cost
Reference No:- TGS02548225

Now Priced at $15 (50% Discount)