At what proportion of actual defects is the the


The cost to do 100% inspection of incoming parts is $0.70 per item and the cost to replace a defect later in the process when the defect becomes obvious is $15.25.

At what proportion of actual defects is the the organization indifferent between 100% inspection, and accepting the lot and replacing the items later in the process?

Express as a decimal rounded to three places.

Request for Solution File

Ask an Expert for Answer!!
HR Management: At what proportion of actual defects is the the
Reference No:- TGS02574888

Expected delivery within 24 Hours