At what project duration do attain lowest total project cost


You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis and are given below:

Activity Immediate Predecessor Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($)
A None 3 2 300 400
B A 3 3 100 100
C A 1 1 200 200
D B and C 3 2 400 550
E D 2 1 500 900
F E 3 3 200 200
G F 2 2 100 100

Total indirect costs for 16 days of project duration: $ 600 Total indirect costs for 15 days of project duration: $ 400 Total indirect costs for 14 days of project duration: $ 200 Total indirect costs for 13 days of project duration: $ 100 At what project duration do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

Answer

16 days

15 days

14 days

13 days