At times a project manager must evaluate proposals from


At times, a project manager must evaluate proposals from identified vendors and make decisions based on the project budget and schedule. It is essential to determine how the organization will determine the best response to the proposal's individual vendors? IRTC has asked you to evaluate the customer service add-on the vendor offered while still in negotiations for this project. The add-on will cost $25,000 and take an additional 4 weeks to install. Your manager has asked for your opinion. The project is tracking along according to schedule and budget.

Question: What stakeholders would need to be involved in this decision-making process? Why?