At the completion of the forward and backward passes the


At the completion of the forward and backward passes, the slack for an activity is given by the

a. difference between early start and early finish

b. difference between early start and latest finish

c. difference between latest start and early finish

d. amount of idle labor on the critical path

Request for Solution File

Ask an Expert for Answer!!
Operation Management: At the completion of the forward and backward passes the
Reference No:- TGS01517989

Expected delivery within 24 Hours