Assuming that one worker is required for each activity


6:Resource -Leveled Gantt Chart

Assuming that one worker is required for each activity, prepare a resource-leveled schedule. What is the maximum number of workers required to finish the project on time? Show all work and provide a completed Gantt chart using Excel.

7: CPM NETWORK ANALYSIS

Given the data in the table below, perform a critical path analysis to determine the project's critical path. Draw a AON project network diagram for the project. Identify all of the possible paths, duration of each path, and identify the critical path. Calculate and indicate the ES/EF schedule, LS/LF schedule, and slack. Show all work and provide a completed Gantt chart of the CPM Network Analysis. Note: Use the drawing tool in Word, Excel or PowerPoint to draw the diagram. Use Excel to create a Gantt chart.

Activity

Duration

Predecessor(s)

A

3 weeks

--

B

15 weeks

A

C

5 weeks

B

D

3 weeks

C

E

6 weeks

B

F

4 weeks

E

G

2 weeks

D, F

8: PERT ANALYSIS

Using the following data values for minimum expected activity durations and maximum expected activity durations, provide a PERT analysis of the network analysis given in question 7. Include all calculations and show all work.

Activity

Minimum Duration

Maximum Duration

A

2

4

B

12

18

C

3

7

D

2

4

E

4

8

F

3

5

G

1

3

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Assuming that one worker is required for each activity
Reference No:- TGS01475321

Expected delivery within 24 Hours