Question - Benny Building, Inc. won a bid for a new warehouse building contract. Below is information from the project accountant.

Total Construction Fixed Price $22,000,000

Construction Start Date June 13, 2012

Construction Complete Date December 16, 2013

As of Dec. 31... 2012 2013

Actual cost incurred $9,500,000 $8,360,000

Estimated remaining costs $8,250,000 $-

Billed to customer $11,000,000 $11,000,000

Received from customer $10,000,000 $9,000,000

Assuming Benny Building, Inc. uses the completed contract method, what amount of gross profit would be recognized in 2013?

$4,140,000

$1,865,352

$1,140,000

$2,215,775