Assume that z is made of two units of a and four units of b


Assume that Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E.

Lead times for purchase or fabrication of each unit to final assembly are: Z takes two week; A,B,C and D take one week each; and E takes three weeks.

Fifty units are required in Period 10. (Assume that there is currently no inventory on hand on any of these items.)

A. Show the bill of materials (product structure tree).

B. Develop an MRP planning schedule showing gross and net requirements and order release and order reciept dates.

 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Assume that z is made of two units of a and four units of b
Reference No:- TGS0564580

Expected delivery within 24 Hours