Assume that product z is made of two units of a and three


Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty two units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.) Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Assume that product z is made of two units of a and three
Reference No:- TGS01296178