Assume that product z is made of two units of a and four


Assume that product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units are required in period 10. (Assume there is currently no inventory on-hand of these items.) a) Show the bill-of-materials (product structure tree) b) Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Assume that product z is made of two units of a and four
Reference No:- TGS01542403

Expected delivery within 24 Hours