Assume that only purchasing costs are being considered


A manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A $ 60,000 B $ 50,000 C $ 60,000 Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Product Annual Demand A B C 1 8,000 3 6 3 2 11,000 1 3 1 3 19,000 5 4 4 4 22,000 3 2 2

Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type. The machines will operate 10 hours a day, 250 days a year.

Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $11 each, B machines have an hourly operating cost of $12 each, and C machines have an hourly operating cost of $10 each. What would be the total cost associated with each machine option, including both the initial purchasing cost and the annual operating cost incurred to satisfy demand?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Assume that only purchasing costs are being considered
Reference No:- TGS01623451

Expected delivery within 24 Hours