Assigned as the project manager to a project which had a


Assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.


You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000

Solution Preview :

Prepared by a verified Expert
Business Management: Assigned as the project manager to a project which had a
Reference No:- TGS0922888

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)