Assign workers to jobs so as to minimize the total time


Five workers are available to perform four jobs. The time it takes each worker to perform each job is given in Table.

 

 

Time (Hours)

 

Worker

Job 1

Job 2

Job 3

Job 4

 

 

 

 

 

1

10

15

10

15

2

12

8

20

16

3

12

9

12

18

4

6

12

15

18

5

16

12

8

12

The goal is to assign workers to jobs so as to minimize the total time required to perform the four jobs. Use the Hungarian method to solve the problem.

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Assign workers to jobs so as to minimize the total time
Reference No:- TGS0683561