Assign the resources from the resource table to the ms


Use the files attached to access:

Project resource table

MS Project file

Respond to the following:

Assign the resources from the resource table to the MS Project

What is the total cost of the project?

Note: Assume that this is a fixed-duration project; After assigning resources, if the duration changes, make sure to change it back to the original.

Resource

Type

Rate

Avail

Planner

Work

$50/hr

100%

Admin support

Work

$40/hr

150%

Sr Engineer

Work

$60/hr

200%

Jr Engineer

Work

$50/hr

100%

Cost analyst

Work

$50/hr

100%

Scheduler

Work

$45/hr

100%

Procurement Specialist

Work

$45/hr

100%

Equipment

Material

$100,000


Installation Contractor

Work

$1,000/wk

100%

Task

Resource

%

2.1

Planner

100

2.1

Admin Support

50

2.2

Planner

100

2.2

Scheduler

100

2.2

Admin Support

50

2.3

Planner

100

2.3

Cost Analyst

100

2.3

Admin Support

50

2.4

Planner

100

2.4

Admin Support

100

3.1

Sr Engineer

200

3.1

Jr Engineer

100

3.2

Admin Support

50

3.2

Procurement Specialist

100

3.2

Equipment


3.3

Installation Contractor

100

4.1

Admin Support

100

4.2

Procurement Specialist

100

4.2

Admin Support

25

 