Arthur meiners is the production manager of wheel-rite a


Arthur Meiners is the production manager of? Wheel-Rite, a small producer of metal parts.? Wheel-Rite supplies? Cal-Tex, a larger assembly? company, with 11,100 wheel bearings each year. This order has been stable for some time. Setup cost for? Wheel-Rite is ?$42?, and holding cost is ?$0.80per wheel bearing per year.? Wheel-Rite can produce 490wheel bearings per day.? Cal-Tex is a? just-in-time manufacturer and requires that 46 bearings be shipped to it each business day.

?a) What is the optimum production? quantity? ?(round your response to the nearest whole? number).

?b) What is the maximum number of wheel bearings that will be in inventory at? Wheel-Rite?

?c) How many production runs of wheel bearings will? Wheel-Rite have in a? year?