Archer construction company began work on a 420000


Question: Archer Construction Company began work on a $420,000 construction contract in 2014. During 2014, Archer incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. At December 31, 2014, the estimated future costs to complete the project total $162,000. Prepare Archer's journal entry to record profit or loss using

(a) the percentage-of-completion method and

(b) the completed-contract method, if any.