Problem:

In a fixed order quantity system (Q-system), the daily demand for a product is approximately normally distributed with a mean of 91.2 and a standard deviation of 23.6 units. The order lead time is 17 days.

Required:

Question: What is the appropriate reorder point (in units) if the target service level is 87.08%?

Note: Be sure to show how you arrived at your answer.