Applying overhead to jobs costing jobs gorman company


Question: Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,640 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows:

                                 Job 877          Job 878          Job 879         Job 880

Direct materials            $14,460          $6,000          $3,500          $1,800

Direct labor                   14,800            8,500           1,750           2,150

Overhead is applied to production at the rate of 80 percent of direct labor cost. Job 877 was completed on October 28, and the client was billed at cost plus 50 percent. All other jobs remained in process. Required:

1. Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October.

2. Calculate the overhead applied during October.

3. Calculate the balance in Work in Process on October 31.

4. What is the price of Job 877?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Applying overhead to jobs costing jobs gorman company
Reference No:- TGS02488768

Now Priced at $15 (50% Discount)

Recommended (96%)

Rated (4.8/5)