annual demand 2400 units ordering cost per


ANNUAL DEMAND = 2400 UNITS
ORDERING COST PER UNIT = RS.4.00/-
UNIT PRICE = RS 2.40/-
STORAGE COST = 2% P.A
INTEREST RATE = 10 % P.A
LEAD TIME = HALF MONTH
CALCULATE ECONOMIC ORDER QUANTITY