Analyzing project with known activity times


Assignment:

The following represents a project with known activity times. All times are in weeks.
Activity Predecessor    Immediate Time
A    -    4
B    -    3
C    A    2
D    B    7
E    C, D    4
F    B    5
1. Using the data in the table above, what is the minimum possible time required for completing the project?
a.) 8
b.) 14
c.) 25
d.) 10
e.) none of the above

2. Using the data in the table above, what is the latest possible time that C may be started without delaying completion of the project?
a.) 0
b.) 4
c.) 8
d.) 10
e.) none of the above

3. According to the table above, compute the slack time for activity D.
a.) 0
b.) 5
c.) 3
d.) 6
e.) none of the above