Analytical questions require a clear development of the


Analytical questions require a clear development of the logic and/or mathematics that lead to the correct answer. A correct answer with no supporting material may be counted as incorrect. Be sure to answer each part (labeled "a", "b", etc.) and show your work in the section provided below each part. The point value for each part is shown.

Answer the questions below with regard to the following table.

ACTIVITY

Immediate predecessor

duration

A

--

6

B

A

20

C

A

5

D

C

2

E

C

6

F

D, E

6

G

B, F

1

(a) draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

(b) List the tasks on the critical path

(c) What is the expected project duration in weeks?

(d) What is the slack for each activity? 

Solution Preview :

Prepared by a verified Expert
Business Management: Analytical questions require a clear development of the
Reference No:- TGS01390272

Now Priced at $20 (50% Discount)

Recommended (90%)