An output of 900 units per shift 75 is desired for a new


A firm uses assembly system and needs answers to the following:

An output of 900 units per shift (7.5) is desired for a new processing system . The system requires product to pass through four stations where the work content at each is 30 seconds . What is the required cycle time you calculated