an operation has a 10 scrap rate as a result 72


An operation has a 10% scrap rate. As a result, 72 pieces per hour are produced. What is the potential increase in labour productivity that could be achieved by eliminating the scrap?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: an operation has a 10 scrap rate as a result 72