An entrepreneur is starting a new business find the


Problem -

An entrepreneur is starting a new business. The activities and times required are given below:

1444_figure.png

a. Find the critical path and project completion time.

b. What are the ES, LS, EF and LF for each activity?

c. How much slack is there in activity D?