An engineer is required to survey a nonrectangular plot of


An engineer is required to survey a nonrectangular plot of land but is unable to measure side UT directly (see Figure 2.11). The following data are taken: RU=130.0m, RS=120.0m, ST=90.0m, angle RST= 115 degrees, and angle RUT= 100 degrees.Calculate the length of side UT and the area of the plot.

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: An engineer is required to survey a nonrectangular plot of
Reference No:- TGS0806967