An embarkment will be constructed with the soil compacted


an embarkment will be constructed with the soil compacted to 95 percent of the max dry density. the borrow material, is deposited at a uniform density of 75 percent of the max dry density. the roadway embankment will require 75,000 cubic yards of fill. how many yards of borrow will be required to complete construction of the embankment?