An electric utility company is considering a re-engineering


An electric utility company is considering a re-engineering of a major hydroelectric facility. The project would yield greater capacity and lower cost per kilowatt-hour of power. As a result of the project, the price of power would be reduced. This is expected to increase the quantity of power demanded. The following data are available:

Effect of Reduced Price of Power

 

Current Price($/kWh)

0.07

Current consumption(kWh/Year)

9,000,000

New Price($/kWh)

0.05

Expected consumption (kWh/year)

12,250,000


What is the annual benefit to consumers of power from this project?