An electric car company operates a manufacturing facility


An electric car company operates a manufacturing facility with 160 robots and 3000 employees. The process produces some 500 vehicles each week. It takes a car about 5 days to move from the beginning of the process to the end. The plant operates for 16 hours per day, 5 days a week. What is the cycle time of the process (in minutes per car)?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: An electric car company operates a manufacturing facility
Reference No:- TGS02870262

Expected delivery within 24 Hours