An assembly line with 17 tasks is to be balanced the


An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate 450 minutes per day.

a. What is the output rate for the line?

b. What is the minimum number of workstations needed if the output rate (in part a) is to be sought?

 