An assembly line requires six tasks to make their product


An assembly line requires six tasks to make their product.

The longest task takes 2.9 minutes to complete, and the total time for all tasks is 13.3 minutes. The line operates 480 minutes per day.

What is the minimum and maximum number of units that can be produced per day?

minimum = 6

maximum = 26

 

minimum = 36

maximum = 80

 

minimum = 36

maximum = 165

 

minimum = 80

maximum = 165