An asphalt mixture is placed and compacted two tests are


An asphalt mixture is placed and compacted. Two tests are taken from the compacted mixture and checked for density. Core #1 had a density of 2403 kg/m3 and an air void content of 6.5%. Core #2 had a density of 2419 kg/m3. What is the air void content of core #2.

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: An asphalt mixture is placed and compacted two tests are
Reference No:- TGS0638729

Expected delivery within 24 Hours