An analyst has timed a metal-cutting operation for 50


An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.7 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 15 percent of job time. Find the standard time for this operation. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)