An analyst has timed a metal-cutting operation for 50


An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16 percent of job time. Find the standard time for this operation. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)

Standard time

minutes

Request for Solution File

Ask an Expert for Answer!!
Business Economics: An analyst has timed a metal-cutting operation for 50
Reference No:- TGS01580278

Expected delivery within 24 Hours