Amortization of prior service cost was 48000 for 2008 what


Question - On January 1, 2008, Prada Corp. adopted a defined-benefit pension plan. The plan's service cost of $300,000 was fully funded at the end of 2008. Prior service cost was funded by a contribution of $120,000 in 2008. Amortization of prior service cost was $48,000 for 2008. What is the amount of Prada's prepaid pension cost at December 31, 2008?

a. $180,000

b. $168,000

c. $72,000

d. $120,000

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Amortization of prior service cost was 48000 for 2008 what
Reference No:- TGS02598135

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)